Introduction
This document provides a detailed plan for the system testing activities to be conducted for the implementation of Two-Factor Authentication (2FA) in the project titled "Implement 2FA - Connor." The purpose of this document is to outline the testing strategy, objectives, scope, and other relevant details to ensure a comprehensive and effective testing process.
Objectives
The primary objectives of the system testing for the "Implement 2FA - Connor" project are:
- To verify that the 2FA functionality is implemented correctly and works as intended.
- To ensure that the 2FA feature enhances the security of user accounts without compromising usability.
- To identify and resolve any defects or issues related to the 2FA implementation.
Scope
The scope of the system testing includes:
- Testing the integration of 2FA with the existing authentication system.
- Verifying the generation and delivery of 2FA tokens via different channels (e.g., SMS, email, authenticator app).
- Ensuring the 2FA process works seamlessly across different devices and browsers.
- Validating the user experience during the 2FA setup and login process.
- Testing the fallback and recovery mechanisms for 2FA.
Test Strategy
The test strategy for the "Implement 2FA - Connor" project includes the following types of testing:
- Functional Testing: To verify the functionality of 2FA.
- Usability Testing: To ensure the 2FA process is user-friendly.
- Security Testing: To validate the security aspects of 2FA.
- Compatibility Testing: To ensure 2FA works across different devices and browsers.
- Performance Testing: To assess the performance impact of 2FA on the system.
Test Plan
Test Environment
The test environment for the "Implement 2FA - Connor" project includes:
- Hardware: Servers, client machines, mobile devices.
- Software: Operating systems, browsers, authenticator apps.
- Network Configurations: Network setups to simulate different user environments.
Test Criteria
- Entry Criteria:
- 2FA feature development is complete.
- Test environment is set up and configured.
- Test data is prepared.
- Exit Criteria:
- All planned test cases are executed.
- All critical and major defects are resolved.
- Test summary report is reviewed and approved.
Test Deliverables
The deliverables for the "Implement 2FA - Connor" project include:
- Test Cases
- Test Scripts
- Test Data
- Test Execution Reports
- Defect Reports
- Test Summary Report
Test Schedule
The high-level schedule for the testing activities is as follows:
- Test Planning: 05/01/2025 - 05/05/2025
- Test Case Design: 05/06/2025 - 05/10/2025
- Test Environment Setup: 05/11/2025 - 05/12/2025
- Test Execution: 05/13/2025 - 05/25/2025
- Defect Fixing and Re-testing: 05/26/2025 - 05/31/2025
- Test Summary Report: 06/01/2025
Resources
The resources required for the testing include:
- Personnel: Test Manager, Test Lead, Test Engineers, Developers, Business Analyst.
- Tools: Test management tool, defect tracking tool, performance testing tool.
- Materials: Test environment setup, test data.
Roles and Responsibilities
Role |
Responsibility |
Test Manager |
Oversee the testing process, manage resources, and ensure adherence to the test plan |
Test Lead |
Coordinate testing activities and manage the test team |
Test Engineer |
Design and execute test cases, report defects |
Developer |
Fix defects and provide technical support |
Business Analyst |
Ensure test cases align with business requirements |
Defect Management
The defect management process involves:
- Logging defects in the defect tracking tool.
- Assigning defects to the responsible developer.
- Tracking the status of defects until resolution.
- Re-testing fixed defects to ensure they are resolved.
Risk Management
Potential risks and mitigation strategies include:
- Delayed Development: Mitigation: Regular status checks and updates.
- Environment Issues: Mitigation: Early setup and validation of the test environment.
- Resource Availability: Mitigation: Ensure backup resources are identified and available.
Communication Plan
Communication Type |
Audience |
Frequency |
Medium |
Owner |
Status Report |
Project Team |
Weekly |
Email |
Test Manager |
Defect Review Meeting |
Key Stakeholders |
Bi-weekly |
Meeting |
Test Lead |
Test Summary Report |
All Stakeholders |
End of Testing Phase |
Document |
Test Manager |
Approval
- Prepared by: Mike Meier
- Email: mikemeier@mad-tech.ai
- Date: 05/07/2025
- Approved by: [Approver's Name]